1MundraOperational Since September 1998Facilities developed:
  • 1 multipurpose jetty with 4 berths
  • Container terminal – 2 berths
  • Terminal T-2 for bulk cargo
  • SBM – 1
Under development/plan:
  • SEZ related development – Development of direct berthing facilities at of Old Mundra Port
  • Ship Building Project
  • Development new basin for additional 12 berths at Mundra Port
  • Development of Coal Terminal for Ultra Mega Power Plant (UMPP)
2PipavavOperational Since 1996Facilities developed:
  • Container berth – 2 berths
  • Bulk terminal – 1 berth
  • Liquid terminal – 1 berth
Under development/plan:
  • Dedicated container terminal
3DahejLNG terminal – operational since February 2004Facilities developed:
  • LNG Import facilities of 5 MMTPA
Under development/plan:
  • 2 LNG tank under construction to enhance capacity from 5 MMTPA to 10 MMTPA
  • Solid cargo port terminal under construction (2 berths)
4HaziraLNG terminal operational since April 2005Facilities developed: LNG import facilities of 5 MMTPAUnder development/plan:
  • Non-LNG terminal to be developed
Awarded Projects
No.PortStatus
1Dholera
  • Environment Clearance obtained
  • Revised DPR from developer is under preparation
  • Land acquisition is under progress
  • Started preliminary survey works
2Poshitra
  • Environment clearance awaiting
  • Private Land Acquisition is in process
  • The company has initiated financial tie up
3Establishment of 3 additional SPMs at Sikka - M/s. RPTL
  • One SPM is constructed and made operational since October 2007
  • Construction of other 2 SPMs are under progress
4Development multipurpose jetty having 2 berths each for solid cargo and liquid cargo
  • Permission is granted vide this office letter dated 21st March 2007
  • Company has initiated detailed studies
5Establishment of 2nd SBM at Hazira
  • Permission is granted by the Board on 13th April 2007
6Extension of captive jetty at Magdalla - M/s. Essar
  • 625 m jetty is constructed and will be operational after getting landing place declaration
  • Company's proposal for dedicated channel and direct berthing port facilities in 550 m length as second phase is principally approved.
  • Dumping of dredged material is approved in principle.
7Extension of captive jetty at Kovaya (Pipavav) - M/s. Ultra Tech Cement
  • Approval is granted by GMB
  • Company has submitted DPR
8Extension of captive jetty at Jakhau - M/s. Sanghi Cement
  • In-principle approval has been granted by GMB
  • Company has started initial studies
9Expansion of port facilities at Pipavav port - M/s. GPPL
  • DPR approved
  • Construction of one more berth for container is commenced
10Cement jetty at Kutch - Gujarat Anjan Cement
  • NOC for carrying out hydrographic survey is issued
11Cement jetty at Kutch - Deepak Cement
  • NOC for carrying out hydrographic survey is issued
12Cement jetty at Kutch - ABG Shipyard Ltd.
  • In principle approval is revived
13Solid Cargo Terminal at Dahej - Adani Petronet Pvt. Ltd.
  • Sub concession agreement signed.
  • Construction work started.
  • GIDC/Dahej SEZ regarding higher cost is to be resolved incl. temporary use of land.
14Indorama captive Jetty
  • Approved in principle by Board
15Ship Building yard at Pipavav
  • Board has granted permission for construction under GMB Act 3(1)
  • Company has submitted DPR and agency for construction is fixed.
Projects under Bidding stage
NoPortStatus
1SimarProposal is under scrutiny at GOG level. LOI will be issued shortly
2Vansi BorsiRevised commercial Bids received. Proposal is being submitted GOG and LOI will be issued shortly
3MithivirdiProposal is under scrutiny at GOG level. LOI will be issued shortly
4BediProposal is under scrutiny at GOG level. LOI will be issued shortly
5MaroliLOI will be issued shortly
6KhambhatLOI is being issued
7MahuvaRevised commercial Bids received. Proposal is being submitted GOG and LOI will be issued shortly
8Dahej (Container and SEZ) Proposal is under scrutiny at GOG level. LOI will be issued shortly
9ModhwaRevised commercial bids has been received. The same will be processed further by GMB.
10SutrapadaNegotiation with Bidder is made at GOG level and the same is under consideration at GOG Leve.
11SPV in existing Magdalla PortTechno Commercial – Legal study to develop/upgrade existing ports in Joint Venture is prepared by the consultants and is under examinations. RFQ document is expected to be issued by March 2008.
12SPV in existing Navlakhi port-
13SPV in existing Okha port-
14SPV in existing Bhavnagar port-
15SPV GMB and GIDC at Dahej-
16SPV for Alang-