Demand-Supply Scenario
2007-082010-112012-132017-182019-20
Demand : Non major Ports Only148226322573740
Traffic# : Non major + Kandla & Vadinar -  --  -
Capacity*@ : Gujarat Ports203303615849990
Capacity@ : GMB + Kandla & Vadinar  -  -  -
Total Supply at Gujarat Ports(MMTPA)(75% of Capacity)153227461637742
Demand- Supply Gap-5-1-139-64-2
It can be seen that till 2017-18, adequate supply is available for the demand that would arise for Gujarat Ports, and only by 2018-19 does the demand catch up with supply available. Thus, it can be said that by 2020 Gujarat Ports would have adequate capacity to meet future cargo demand